試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-2
考試中心《信息系統(tǒng)項目管理師-pmp練習題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

The chief architect of the project and the key client representative cannot cooperate on the project. Which adversely impacts the project’s progress. What should the project manager do to address this issue ?
A、Determine a senior staff to act as an arbitrator between the architect and the clients’ representative.
B、 Request the architect’s supervisor to discuss this problem with him/her.
C、 In consultation with the project sponsor to replace the key client representative.
D、 Identify the chief architect and the common interests of the clients’ representative, determine possible solutions.