扫黑风暴在线观看免费完整版未删减|电影苹果完整版未删减内容|国产首页|沙丘国语电影完整版在线观看,国产一级影片,老炮儿电影未删减完整版下载,www 俺来也

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(1)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(1)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

The inter-county connector highway had been in the proposed stage for decades. Neighborhoods have been concerned about ecological impacts, congestion, pollution and noise. In order to gain acceptance, certain community specifications need to be met. Finally, the community and local government have reached an agreement and the project is officially progressing. In order for the project to be successful, what must the project manager do?
A、Continuously solicit input from community stakeholders
B、Obtain legal representation incase specifications are not met
C、Communicate with community stakeholders regarding how the specifications are being met
D、Increase the budget since materials will be more costly


相關試題

推薦文章